SediVision Case Study: Blacks Ford Water Reclamation Facility
SediVision® has published a wastewater case study on a project conducted for the Blacks Ford Water Reclamation Facility.
JEA hired Ardurra Group, Inc., to upgrade and expand the Blacks Ford Water Reclamation Facility (BFWRF). SediVision® was contracted by Ardurra to provide a grit accumulation analysis for the facility’s existing infrastructure.

“SediVision was able to help us avoid a significant capital cost for our client (JEA). We were very pleased with the process and results because it provided the data that we needed to confidently make that decision.”
David Rasmussen,
Ardurra Client Service Manager
SCOPE OF WORK
Deploy SediVision® technology to scan approximately 56,000 square feet in two BNR trains. Deliver to Ardurra informed data regarding the quantity and location of debris within the existing tanks.
DELIVERABLE
SediVision® results revealed the location and quantity of debris within the BNR trains. The amount was calculated to be approximately 815 cubic yards.
CONCLUSION
Equipped with hard data, Ardurra was pleased with the current status of the tank and could confidently advise JEA that investment in a grit removal system at BFWRF was not necessary at this time.
Read the full SediVision/ Blacks Ford Water Reclamation Facility case study.
Other related case studies:
More Recent Posts

Online Tank Cleaning plus 6 more Water and Wastewater Services

Continuing Education Opportunities with ARWA Apprenticeship Program & Events 2025

DEP Secretary Lambert: Governor DeSantis’ Budget Recommendations Deliver on His Commitment to Conservation

Hidden Lessons in Life
Subscribe
Get news delivered straight to your inbox the day it gets published."*" indicates required fields